Project44 provides an extensive container tracking in the form of incoming status messages on the EDI-Status tab in the order after you have configured the interface.

Requirements for the reception of status messages of the provider project44:

  • a contract between you and project44,
  • a contract with CargoSoft for the configuration of the interface (subject to charge)
  • supply of a service that is accessible in the internet.

This program can be found on the Status request tab of a file.

Status codes are administered in  the status events.



ADMIN → STATUS TYPES → STATUS EVENTS

The required status codes and settings for the status request for provider project44 are entered in the basic data along with the configuration of the interface.

  • These settings can be changed individually as necessary.
  • In our example, the old name OCEANINS is still used for hte interface - the explanation in the Name field refers to project44.


Image Added


Status messages and codes

The following status messages are transmitted and processed on the EDI status tab:

Status codeStatus description
10POL changed
100Shipment initialized
101Shipment invalid
102Shipment expired
103Shipment re-initialized
104Shipment AIS data flushed and re-generated
11T/S port 1 changed
110Container removed from booking
12T/S port 2 changed
13T/S port 3 changed
14T/S port 4 changed
15POD changed
16Port changed (rerouting)
17Number of transshipments changed (rerouting)
20Location update
25Discrepancy between contracted and reported ETA at POD
26Discrepancy between contracted and reported ETA at place of delivery
3Vessel approaching POD (time)
4Rollover warning (vessel change)
5Vessel entered POD
6Vessel moored in POD
7Vessel approaching POD (distance)
8Vessel ETA changed while approaching POD
9New actuals received or actuals changed
CDCContainer delivery to consignee
CDDContainer discharge at final POD
CDT1,CDT2,CDT3,CDT4Container discharge at T/S port1,2,3,4
CERContainer empty return to depot
CGOContainer departure from final POD (Gate-out)
CIFContainer arrival at last inland facility (Gate-in)
CLT1,CLT2,CLT3,CLT4Container loaded at T/S port 1,2,3,4
COFContainer departure from last inland facility (Gate-out)
VADVessel arrival at final POD
VAT2,VAT3,VAT4Vessel arrival at T/S port 2,3,4
VDT1,2,3,4Vessel departure from T/S 1,2,3,4


Status request tab

The queries are sent via the Status request tab in the order.

The tab must be integrated into the order via the mask editor.

Image Added


Send status request

A request can be made by means of the container number, booking number and/or the B/L number.

Entry of the SCAC code is required.

By setting the checkbox request and saving, the status request is sent to the provider.


EDI Status tab

If the request has been activated, the program shows the current data about the container on the EDI-Status tab in the order.

The tab must be integrated into the order via the mask editor.

Display responses

After an incoming status message has arrived, the system prepares the status messages and checks whether the container number is already available in the goods description of the order.

If this is not the case, the system automatically creates a new package line (level 1) with the transmitted container number and the packaging code.

In case of multiple containers that have not been entered in the file, the system will enter a new package line (level 1) per container in the goods description.


Deactivate status request

You also have the option to deactivate the status request with a cancelation message on the Status request tab.

  • After the transport has been completed, the status transmission is automatically set up for the containers of the order.